What is the total float of an activity on the baseline schedule's critical path?

Prepare for the CMAA Certified Associate Construction Manager Test. Use flashcards and multiple-choice questions with explanations and hints. Achieve success on your first try!

Multiple Choice

What is the total float of an activity on the baseline schedule's critical path?

Explanation:
Total float shows how long an activity can be delayed without delaying the project's finish. For an activity on the baseline schedule’s critical path, there is no room to delay without impacting completion date. In other words, the early dates equal the late dates (ES = LS and EF = LF), so the total float is zero. This zero float means any delay on that activity pushes the project end date, which is why those activities are on the critical path. Activities not on the critical path have positive total float, indicating some scheduling flexibility. Even with multiple critical paths, the activities on any one of them still have zero total float.

Total float shows how long an activity can be delayed without delaying the project's finish. For an activity on the baseline schedule’s critical path, there is no room to delay without impacting completion date. In other words, the early dates equal the late dates (ES = LS and EF = LF), so the total float is zero. This zero float means any delay on that activity pushes the project end date, which is why those activities are on the critical path. Activities not on the critical path have positive total float, indicating some scheduling flexibility. Even with multiple critical paths, the activities on any one of them still have zero total float.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy