The date when the facility may be used for its intended purposes, even though all work is not fully completed is:

Prepare for the CMAA Certified Associate Construction Manager Test. Use flashcards and multiple-choice questions with explanations and hints. Achieve success on your first try!

Multiple Choice

The date when the facility may be used for its intended purposes, even though all work is not fully completed is:

Explanation:
Substantial completion is reached when the building is ready for its intended use, even though some minor finishing tasks or corrections may still be outstanding. At this point the owner can occupy and begin using the facility for its normal purposes, and the project can transition from active construction to occupancy. The remaining work is usually limited to a punch list and does not prevent use, though the contractor still completes those items over time. This milestone often changes practical responsibilities—risk, insurance, and certain costs may shift to the owner, and the defects liability period typically starts. This differs from final completion, which means everything is finished and all contractual obligations are fully satisfied, with no remaining work or defects. Temporary occupancy refers to using space under a temporary or limited arrangement while the project is still largely under construction, which is not the same as being able to use the facility for its full intended purpose. Practical completion is a term used in some contracts to denote a similar state of readiness, but the description given—being able to use the facility for its intended purposes despite incomplete work—best matches substantial completion.

Substantial completion is reached when the building is ready for its intended use, even though some minor finishing tasks or corrections may still be outstanding. At this point the owner can occupy and begin using the facility for its normal purposes, and the project can transition from active construction to occupancy. The remaining work is usually limited to a punch list and does not prevent use, though the contractor still completes those items over time. This milestone often changes practical responsibilities—risk, insurance, and certain costs may shift to the owner, and the defects liability period typically starts.

This differs from final completion, which means everything is finished and all contractual obligations are fully satisfied, with no remaining work or defects. Temporary occupancy refers to using space under a temporary or limited arrangement while the project is still largely under construction, which is not the same as being able to use the facility for its full intended purpose. Practical completion is a term used in some contracts to denote a similar state of readiness, but the description given—being able to use the facility for its intended purposes despite incomplete work—best matches substantial completion.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy