In a design-bid-build project, who is typically responsible for recommending risk responses to the owner when a new risk is identified?

Prepare for the CMAA Certified Associate Construction Manager Test. Use flashcards and multiple-choice questions with explanations and hints. Achieve success on your first try!

Multiple Choice

In a design-bid-build project, who is typically responsible for recommending risk responses to the owner when a new risk is identified?

Explanation:
Understanding risk management in a design-bid-build project is key. When a new risk is identified, the construction manager, acting as the owner’s representative, takes the lead in evaluating the risk and developing recommended responses. The CM maintains the risk register, analyzes how likely and how severe the risk could be, and proposes practical strategies to address it—such as avoiding, mitigating, transferring, or accepting the risk—along with any required contingencies. The CM then presents these recommendations to the owner and coordinates input from the design team and construction team to arrive at a decision. The owner ultimately approves the chosen course of action, but the responsibility for formulating and communicating the risk response lies with the construction manager. The architect and contractor may flag risks within their domains, but they do not typically take the lead on recommending overall risk responses to the owner.

Understanding risk management in a design-bid-build project is key. When a new risk is identified, the construction manager, acting as the owner’s representative, takes the lead in evaluating the risk and developing recommended responses. The CM maintains the risk register, analyzes how likely and how severe the risk could be, and proposes practical strategies to address it—such as avoiding, mitigating, transferring, or accepting the risk—along with any required contingencies. The CM then presents these recommendations to the owner and coordinates input from the design team and construction team to arrive at a decision. The owner ultimately approves the chosen course of action, but the responsibility for formulating and communicating the risk response lies with the construction manager. The architect and contractor may flag risks within their domains, but they do not typically take the lead on recommending overall risk responses to the owner.