An addendum is normally issued when?

Prepare for the CMAA Certified Associate Construction Manager Test. Use flashcards and multiple-choice questions with explanations and hints. Achieve success on your first try!

Multiple Choice

An addendum is normally issued when?

Explanation:
Addenda are issued to modify, clarify, or add information to bidding documents. They must be released before bids are submitted so every bidder has the same information and can bid on an accurate, up-to-date package. If changes were made after bids are opened, it would be unfair to some bidders and could require extending the bid deadline or re-bidding, which defeats the purpose of providing a consistent set of documents. During construction or after award, changes are handled differently (such as change orders or field directives), not through addenda to the bidding documents. So the normal time for issuing an addendum is before bids are received.

Addenda are issued to modify, clarify, or add information to bidding documents. They must be released before bids are submitted so every bidder has the same information and can bid on an accurate, up-to-date package. If changes were made after bids are opened, it would be unfair to some bidders and could require extending the bid deadline or re-bidding, which defeats the purpose of providing a consistent set of documents. During construction or after award, changes are handled differently (such as change orders or field directives), not through addenda to the bidding documents. So the normal time for issuing an addendum is before bids are received.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy