A claim in the context of a construction contract refers to a formal request by a contractor for additional compensation, time, or other relief, based on the terms and conditions outlined in the contract documents.

Prepare for the CMAA Certified Associate Construction Manager Test. Use flashcards and multiple-choice questions with explanations and hints. Achieve success on your first try!

Multiple Choice

A claim in the context of a construction contract refers to a formal request by a contractor for additional compensation, time, or other relief, based on the terms and conditions outlined in the contract documents.

Explanation:
A claim in construction contracts is a formal request by the contractor for additional compensation, time, or other relief that is grounded in the terms and conditions of the contract documents. This means the contractor believes entitlement arises because of changes, unforeseen conditions, delays, or disruptions that the contract provisions cover, and the request follows the contract’s procedures for notices and documentation. It’s a mechanism to seek relief when events or changes aren’t simply agreed changes to the contract, rather a dispute over entitlement that may require assessment or dispute resolution. This differs from a change order, which is a negotiated modification to the contract itself, and from an information request (RFI), which seeks clarification rather than relief.

A claim in construction contracts is a formal request by the contractor for additional compensation, time, or other relief that is grounded in the terms and conditions of the contract documents. This means the contractor believes entitlement arises because of changes, unforeseen conditions, delays, or disruptions that the contract provisions cover, and the request follows the contract’s procedures for notices and documentation. It’s a mechanism to seek relief when events or changes aren’t simply agreed changes to the contract, rather a dispute over entitlement that may require assessment or dispute resolution. This differs from a change order, which is a negotiated modification to the contract itself, and from an information request (RFI), which seeks clarification rather than relief.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy